Get in touch Panel login

Industry and Manufacturing

A higher kWh figure does not mean efficiency fell. In a factory consumption moves with production; until measurement is normalised against output, no decision stands up to scrutiny.

Get in touch

Baseline

Did consumption rise, or did output?

In a factory, consumption and production move together. In a month when output drops, the bill drops too, and that is not a saving. The reverse holds as well: a higher bill in a month with an extra shift is not waste.

The panel separates the two. A baseline is frozen from a reference period, expected consumption for each month is computed from production and weather data, and the difference is written in both percent and kWh.

  • Variables: output volume, degree days, operating hours
  • The baseline is frozen and never quietly revised
  • The cumulative curve shows savings as they build

A descending curve is good news: every month consumed less than expected. This curve goes straight into ISO 50001 internal audits and efficiency grant applications as evidence.

Cumulative Saving

Σ(actual − expected)
Schematic: a descending curve is accumulated saving. Every upward break is an event to investigate.

Compressed air

A fifth of the bill leaves through one room

Compressed air is the most expensive form electricity takes in a plant. In most factories the compressor room accounts for around a fifth of total consumption, and a large share of that leaves through leaks in the distribution lines.

Measuring compressor power alone is not enough. Without flow and pressure alongside it, specific energy in kWh per cubic metre cannot be computed, and without that figure nobody knows which machine produces expensive air.

  • Power, flow, pressure and temperature per machine
  • Specific energy compared against manufacturer data
  • An empty-plant test measures real leakage

Two machines in the same room produce the same air at different costs. The catalogue figure is the target, the measured figure is the truth, and the gap is either maintenance or loading.

Compressor Room

specific energy · kWh/m³
MachineLoad %Actual kWh/m³Catalogue kWh/m³
Screw 132 kW 86 0.142 0.108
Screw 90 kW 64 0.112 0.106
Screw 75 kW 41 0.118 0.109
Standby 55 kW 0 0.000 0.114
Schematic: if specific energy drifts as load rises, the problem is the machine, not the pipework.

Rollout

How far down does measurement go?

Measurement in a factory starts at the main meter but does not end there. How many points you need depends less on the size of the site than on how many questions you want answered.

If the only question is whether the bill is correct, the main meter suffices. If you want consumption per line, you go down to the distribution boards. If you want to know whether the compressors are efficient, flow and pressure sensors join the room.

  • Main meter and transformer outputs are always included
  • Plant rooms are metered separately
  • Line-level breakdown is optional

The list is drawn up together during the site survey. The ranges below reflect commonly seen sizes; the exact count depends on how the boards are laid out.

Measurement Points

by plant size
  • Small plant 12points main board plus plant rooms
  • Mid-size 26points line-level breakdown added
  • Large plant 44points multiple transformers and rooms
  • Compressor room 9points power, flow, pressure, temperature
Schematic: the green band is the common range, the bar a typical value. The exact list comes out of the survey.

Grants

Which project goes into the funding application?

An efficiency grant application asks you to show that a substantial investment pays back quickly. The weakest part of such a file is almost always the same: the measurement behind the savings claim.

Monitoring settles that from the outset. Because the panel already records where waste sits and how much of it there is, candidate projects are ranked on measured baseline data rather than estimates. The AI assistant draws the shortlist from that record, with the evidence and the payback period written next to each item.

  • Candidates come from measured baseline consumption
  • Payback computed on real prices and real load
  • Once implemented, the gain is verified by the same measurement

Compressor rooms, boiler houses and chiller plant sit at the top of that list; together they account for more than half the bill in most factories. Grant or no grant, the same list is the input to capital planning.

Candidate Screening

from measurement to application
  1. 24 projects Opportunities flagged by the panel from deviation, leak and out-of-hours records
  2. 14 projects Confirmed by measurement site measurement supported the assumption
  3. 8 projects Needing investment items fixed by a setting left the list
  4. 5 projects Payback under 7 years on real prices and real load
  5. 3 projects Entering the application the measurement record is the annex

3 projects reach the file · est. £192k/yr

Schematic: the opportunity list narrows through measurement. Every dropped item keeps a record of where it fell out.

Control

Switch off what you can see

A good share of out-of-hours base load in a factory comes from systems waiting to be switched off: line lighting left on over the weekend, a fan idling, a tank heater running continuously.

The remote control module ties those points to the shift calendar. The schedule comes from the plant’s own working calendar; when the shift pattern changes, the calendar changes and the rules stay put.

  • Lighting and ancillary equipment on the shift calendar
  • Secondary load shedding as the capacity limit approaches
  • Critical process circuits marked view-only

Every controlled point is also metered: the job is not done until the power is seen to fall to zero after switching.

Shift Calendar

week · lighting and ancillaries
  • Mon
  • Tue
  • Wed
  • Thu
  • Fri
  • Sat half shift
  • Sun kapalı security lighting only

shift schedule solar calendar ·haftada 107 saat açık

Schematic: solid blocks are the shift schedule, hatched blocks follow sunset. When the shift pattern changes the calendar changes, not the rules.

Which modules work in a factory

Module What it does here
Compressed Air Specific energy, leak tests, set pressure, pressure drop
Chillers and Cooling Process cooling COP, tower approach, part-load behaviour
Energy Performance and ISO 50001 Production-normalised baseline, deviation, audit-ready record
Power Quality Harmonics, power factor charges, voltage events
Energy Consumption Transformer, area and machine breakdown, out-of-hours load
Bill Validation Line-by-line comparison, deviation alerts
Remote Control Shift calendars, load shedding at the capacity limit
AI Assistant Candidate project shortlist, direct answers on deviations

What surfaces first

Three things show up in the first month on almost every industrial site. The first is out-of-hours base load: power drawn while production is stopped, higher than anyone expected. The second is compressed air leakage, visible as compressors loading in an empty plant. The third is power factor exposure, where compensation cannot keep up with shift changes.

None of the three needs capital investment. They need measurement. Unmeasured, none of them is noticed; measured, all of them are fixed by an operating decision.

Let us measure what is happening on your site.

In a one-hour call we look at your existing setup and set out exactly which measurement points are needed and what you would be able to see.

Get in touch